– CONSTRUCTION OF SHEEP SHED RAM CENTRE AT SHEEP DEVELOPMENT FARM NAGWAIN DISTT. MANDI H.P (ANIMAL HUSBANDRY)

  • A/A & E/S accorded – Rs. 2.00 Cr.
  • Amount deposited by Animal Husbandry Department – Rs. 1,77,62,650/-
  • The contract was awarded to Sh. Rishi Rajan Gupta vide this office letter No. RTDC/Sheep Farm Nagwain/2019-957-67 dated 27th December, 2019.
  • Time period for completion of work – Six Months.
  • Status:- completed and handed over

– SHIMLA SMART CITY PROJECTS
1. Construction of Staircase near Auckland Boys School

  • Project Cost – 15 lacs Completion cost- 12 lacs
  • Contractor -M/S Hukum Singh
  • Status – Completed and handed over during 02/2021

2. Construction of vending zone in Vikasnagar and Khalini

  • Project Cost – 52 lacs Awarded amount- 41 lacs
  • Contractor -M/S J D Power Solution Mohali
  • Status – 95% completed finishing going on in Vikasnagar and FCA case pending for Khalini
  • Completion date – 31-03-2021 for Vikasnagar

3. Construction of pre-engineered Book Café Chotta shimla

  • Project Cost – 65 lacs Awarded amount- 36 lacs
  • Contractor -M/S Vidya Infrastructure and Developers Solan HP
  • Status – 80% completed finishing going on.
  • Completion date – 30-04-2021

4. Construction of pre-engineered Commercial Complex at Kasumpti

  • Project Cost – 1.68 Cr. Awarded amount- 84 lacs
  • Contractor -M/S Suri Engineers
  • Completion date – 30.04.2021
  • Status – Foundation and PEB Completed.
  • Erection of LGSF in progress.

Construction of Sheep Shed at Sheep Development Farm
Work for construction of Sheep Shed (240 sheep capacity) with associated structures in ram center at Sheep Development Farm, Nagwai, Mandi was awarded to Sh Rishi Rajan Gupta, Class ‘A’ Contractor. 60% work has been completed and the remaining work is in progress.


Shimla Smart City Projects

  • Construction of vending zones at different locations in Shimla city.
  • Construction of Book café at Chaura Maidan.
  • Construction of Commercial Complex Kasumpti Shimla in Prefab Light Gauge Steel Frame Technology.
  • Engineering, manufacturing, procurement, installation, testing and commissioning of
    • Lifts and travelators from Lakkar Bazaar bus stand to The Ridge in Shimla
    • Lifts at Metropol Parking Building and Old Bakery Building under Smart City Area-based development.
    • Escalators at Jakhoo Temple Shimla under Smart City Area-based development including comprehensive operations & maintenance
    • Lifts from Auckland area to Police Chowki Lakkar Bazaar
Tenders

Tender Archive